NW-S Crisis response BCP
[Assumed risk:Air Pollution]
1.About this BCP proposal
-
1-1.Purpose
BCP (Business Continuity Plan) is a plan for companies to continue their business in the event of an emergency such as a natural disaster, a fire, or a terrorist attack, to minimize the loss of the company's assets, to continue important business, or to resume work as quickly as possible, in the event of an emergency such as a natural disaster, a fire, or a terrorist attack.
This BCP clarifies the action plan of the company's related functions in advance in order to minimize damage in the event of air pollution, make decisions on emergency responses when limited production of air pollution expands, and quickly and accurately implement the actions of each department.
-
1-2.Basic Policy
Ensure the lives and safety of employees and their families
Capture signs of air pollution and implement appropriate initial responses
Reduce the impact on business continuity plans and the damage situation
Cooperate with the government and peripheral companies to contribute the early stabilization of society and the region
-
1-3.Objective
No more than 3 working days of the production downtime(Restart in the shortest period approved by local government)
"0" Disease caused by air pollution.
"0 day" Customer production stop -
1-4.Scope
The target company is NSK-Warner (Shanghai)
-
1-5.Publish to
Head of Departments of the Company and members of the Crisis Committee Criss Management liaison for each department of the Company
-
1-6.Management of distribution destinations and confidentiality obligations
Administrative officer: All distribution destinations
Confidential classification:confidential
Confidentiality restrictions: No electronic document transfer, No copy issuance
-
1-7.Contact
NSK-Warner(Shanghai) Crisis Committee
2. Preventive measures
-
2-1.Disaster assumptions
This BCP assumes that a serious air pollution disaster has occurred, and the following is an example of air pollution in Shanghai, which generally occurs between October and January of the following year. Generally, the yellow warning limits production by 30%, the orange warning limits production by 40%, and the red warning limits production by 50%. When the Fengxian District Ecological and Environmental Bureau (through the Management Committee of the Development Zone) has other requirements, it shall be implemented in accordance with the requirements of the local government.
-
2-2.Disaster mitigation measures
Based on the assumed disasters of 2-1, in the event of a crisis, overall mitigation measures must be implemented in advance to minimize damage loss
For details, please refer to BCP Appendix (2) Disaster Mitigation List.
3.Responding of a crisis occurred
-
3-1.Emergency response system
(1) This is the company's countermeasure system in the event of a crisis. For details, please refer to "BCP Appendix (3) Emergency Countermeasure System".
Commander of the NW-S Crisis Management Committee is the General Manager, Assistant of Commander is the Minister of Manufacturing, Secretary is the Director of General Affairs and Personnel Dept. The heads of each department are members of the Crisis Management Committee and are responsible for the crisis management of their departments.
(2) Responsibilities of each department
The necessary functions and basic responsibilities for a countermeasure system in the event of a crisis are as follows.
Organization / Function Responsibility Crisis Management Committee Building a disaster prevention management system
Confirmation of disaster mitigation goods
Confirmation of disaster mitigation measures in each department
Establishment of a coordination and supervision response mechanism in the event of a disasterEnvironment Committee Gather information about air pollution
Confirm the weather forecast
To the government's liaison window
Training, rescue and limited production exemption application in the event of air pollution
Plan for commute way that reduces pollutionProduction control Plan for reduce production
Prepare to increase inventoryGeneral Affairs and Human Resources Training self-protection
Prepare protective goods such as masksManufacturing Dep. Development of multi-skilled employees
Make an employee alternative planPurchase / Production control Grasp of logistic risks
Make a logistic alternative planFinancial affairs Communicate with insurance companies and familiarize the relevant compensation business Employees Training arrange a self-protection
Training in communication with the top and bottom
Training follow the instructions for an orderly action(3)Emergency response team establishment and operation guidelines
Item Contents Standards Set up according to the judgment of the commander of the Crisis Management Committee Location No1.Meeting room Method The Secretariat use emergency contact networks or other ways to notify the meeting places and times to emergency response team members.
If in an emergency, not possible to gather at a fixed location, contact the emergency response team member with a specific meeting method and communication means to replace it.Holding meetings The Emergency Response team hold the regular meetings after established, an extraordinary meeting shall be convened at special case. Decide by the top of the Crisis Management Committee. Operating guidelines The members of each team report directly to the Crisis Management Committee.
Strictly adhere to and implement the decisions and instructions of the Emergency Response Team.
Each department is required to report to the Crisis Management Committee on the information collected and the response to the disaster
Damage Information collected by each department should be report to the committee
Regarding worker commander evacuation, work plan and production plan, it decides by chairman according to the customers’ response plan. In addition, the secretariat will notify all members of the company.
-
3-2.Basic response of the company ( list )
From the beginning of the air polluting warning until recovery, the basic correspondence at each stage is described below.
For details, please refer to "BCP Paper (4) Actions at Each Stage in the Event of a Crisis (List)"
stage definition Basic correspondence Precursor period After National Day, entered a period of high air pollution. Confirm the preparation for disaster prevention mitigation in each department.
Monitor the situation, raise inventory and buy masks.Alarm period Set conditions for limiting production by the Environmental Protection Bureau Coordinate the preparation of departments.
Issued reminders of attention, outdoor wearing masks, etc.;Disaster period Air pollution yellow warning (AQI >300) Implement the FP 30% limited production by Environmental Protection Agency.
report to NSK CHINA Crisis Management CommitteeAir pollution Orange warning (AQI >400) Implement the FP 40% limited production by Environmental Protection Agency.
report to NSK CHINA Crisis Management CommitteeAir pollution red warning (AQI >450) Implement the FP 50% limited production by Environmental Protection Agency.
report to NSK CHINA Crisis Management CommitteeRecovery period after disaster Canceled limiting production by the Environmental Protection Bureau Recovery production activities and report to NSK CHINA Crisis Management Committee
-
3-3.Report information (signs at the time of air pollution)
•The Crisis Management Committee reports to CHQ the details of the damage forecast, the results of the disaster, measures and support requests taken by the Company, etc.
•Reporting standards and reporting formats.
Please refer to「BCP enclosure(5) Crisis Report Regulations &Format」.•・ For external inquiries from customers, media, and other local companies, it is necessary to consult with the NSK CHINA Crisis Management Committee on the corresponding guidelines before replying to specific countermeasures, disasters, and recovery.
4. On-premises deployment
-
4-1.Methods of informing employees
Education
Providing regular train to management and ordinary employees to thoroughly convey the contents of the BCP. According to the actual needs, external vendors who require access to the company also need to understand the content.Announcement
The BCP is stored in the safe dojo for demonstrations for staff to learn -
4-2.Training
Crisis Management Committee members and related employees
Training and practices regularly when an emergency response team set up.Training frequency: once a year.
Review of countermeasures and systems
Through training, identify the deficient points and reviewed timely